Benefits
-
The
Hamannwall
system provides a cost competitive
alternative to conventional building methods by removing
the majority of on-site work.
-
The factory produces, large single-spanning lightweight
wall elements, that are easily and speedily erected.
-
A 12 meter by 3 meter by 123 millimeter
Hamannwall
panel
weighs approximately 1.5 tones compared to a similar
size concrete panel that would weigh 10.5 tones.
-
As a load-bearing walling element
Hamannwall
has an
installed cost of about half that of precast concrete
and the finish of
Hamannwall
is superior to an equivalent
off-form, precast-concrete or insitu wall panel.
-
Depending on the wall layout, a
Hamannwall
panel when
concrete filled onsite, can support between twelve and
twenty storeys thus eliminating the need for columns and
floor beams.
|
Hamannwall saves considerable time and money
-
The walls of an average 150m²
Hamannwall
house can be erected in
3-5 hours with just 3 people and a crane.
-
Assembling 3-4 walls per hour is easily achievable with
Hamannwall.
-
Hamannwall
panels of up to 3 meters can be installed manually
without a crane.
-
For
Hamannwall
panels of up to 6 meters a forklift can be used
and for larger panels, up to 12 meters, a crane is recommended.
-
The electrical wiring and plumbing services are placed in the
Hamannwall
cavity, avoiding the need for external fixing. This
saves time traditionally spent to channel or groove these
services in a conventional wall.
-
Hamannwall
is a load bearing system. With multi storey
construction, the walls are filled with concrete after the
services are installed.
-
Even when filled with concrete,
Hamannwall
is more than 20%
lighter than conventional brickwork which means lower foundation
costs.
The overall process
The overall process from the manufacture of the
Hamannwall
panels to
their final erection to form load-bearing walls for a building project
is generally as follows:
-
Using the
Hamannwall
design guidelines the
Hamannwall
walling
requirements are analyzed by a suitably qualified structural
engineer and the Architectural and Engineering drawings prepared
indicating plan layouts, cross-sections, reinforcements, set
downs and edge details.
-
Whole
Hamannwall
panels are manufactured in the factory in a
single panel twelve meters long by three meters high (12,020 mm
X 3050 mm) and a full cutting schedule including panel
elevations and transportation-stillage load sheets are prepared
based upon the design drawings.
-
Using a numerically-controlled table-mounted saw, the panels are
cut to specified dimensions within a tolerance of 5mm. This will
include openings for doors and windows.
-
Where required, galvanized steel metal closures are inserted at
the factory to the panel ends and openings.
-
Between five and eight ‘processed’
Hamannwall
panels are loaded
vertically, to maximize the transportable volume, on to a
transport-stillage.
-
Several full stillages, often containing up to 500 square meters
of ready-to-install
Hamannwall
panels, are loaded onto a
semi-trailer for transportation to the building site.
-
The stillages are unloaded, positioned and stabilized on
prepared flat ground near the construction site in readiness for
erection.
Erecting Hamannwall
After completion of the foundation or the concrete suspended floor onto
which
Hamannwall
is to be positioned, the builder’s surveyors establish
and mark all main grid lines.
-
Using the Architectural layout drawings a trained
Hamannwall
erection crew marks out the walling positions in reference to
these grid lines.
-
For the first floor the concrete foundation is drilled and
starter bars are epoxied into place. For subsequent floors
starter bars extend from the panel below.
-
Weighing up to five tones the laden stillage, containing the
cut
Hamannwall
panels selected for erection, is then lifted by
crane onto the concrete floor or foundation prepared to receive
the panels.
-
One by one the cut
Hamannwall
panels are decanted from the stillage by crane and placed into their final position, propped
and then connected in accordance with the installation
guidelines.
-
To construct the next suspended floor spanning between the
load-bearing
Hamannwall, formwork is installed and propped. After
this it is used as staging to pump concrete into the cells of
the
Hamannwall.
-
Whilst still plastic, starter bars are placed in the concreted
cells in readiness for the next floor of
Hamannwall
panels.
-
Slab reinforcement is placed on the formwork and the concrete
poured for the next suspended floor.
|